PK0-004 · Question #601

Which of the following metrics are used to determine a project's EAC?

The correct answer is C. Planned costs minus actual costs. EAC (Estimate at Completion) represents the remaining estimated budget for a project. It is calculated by subtracting actual costs (what has already been spent) from the planned costs (the original budget). This gives the project manager a forward-looking figure of what remains…

Project management concepts

Question

Which of the following metrics are used to determine a project's EAC?

Exhibit

PK0-004 question #601 exhibit

Options

  • ABaseline costs plus actual costs
  • BForecasted costs plus actual costs
  • CPlanned costs minus actual costs
  • DForecasted costs minus actual costs

How the community answered

(62 responses)
  • A
    3% (2)
  • C
    95% (59)
  • D
    2% (1)

Explanation

EAC (Estimate at Completion) represents the remaining estimated budget for a project. It is calculated by subtracting actual costs (what has already been spent) from the planned costs (the original budget). This gives the project manager a forward-looking figure of what remains to be spent. Options A and B are incorrect because adding costs together yields a total spent or forecasted total, not a remaining estimate. Option D (forecasted minus actual) could represent a variance but is not the standard EAC formula.

Topics

#earned value management#EAC#cost forecasting#project metrics