A project sponsor asks if a construction project can be accelerated to meet a new timeline. The project manager analyzes the schedule and finds insufficient float to accommodate the new delivery…

The correct answer is C. Crash. Crash is a method in project management that helps you speed up the timeline of a project through the addition of resources.

Project management concepts

Question

A project sponsor asks if a construction project can be accelerated to meet a new timeline. The project manager analyzes the schedule and finds insufficient float to accommodate the new delivery date. If more resources are provided, which of the following strategies would BEST help to achieve the new date?

Options

  • AFast track
  • BBurn
  • CCrash
  • DReduce durations

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    83% (25)
  • D
    3% (1)

Explanation

Crash is a method in project management that helps you speed up the timeline of a project through the addition of resources.

Topics

#crashing#schedule compression#resource management#critical path