PK0-004 · Question #60

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the…

The correct answer is C. Schedule variance. Schedule Variance (SV) is the earned value management metric that compares Earned Value to Planned Value and expresses the result as a dollar figure.

Tools and documentation

Question

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?

Options

  • ACost performance index
  • BRisk mitigation
  • CSchedule variance
  • DCost variance

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    13% (5)
  • C
    76% (29)
  • D
    3% (1)

Why each option

Schedule Variance (SV) is the earned value management metric that compares Earned Value to Planned Value and expresses the result as a dollar figure.

ACost performance index

The Cost Performance Index (CPI) equals EV divided by AC and produces a dimensionless efficiency ratio, not a dollar-figure difference, and it compares earned value to actual cost rather than to planned value.

BRisk mitigation

Risk mitigation refers to actions taken to reduce the probability or impact of identified risks and has no relation to earned value calculations or performance measurement.

CSchedule varianceCorrect

Schedule Variance is calculated as EV minus PV (SV = EV - PV) and is denominated in currency, making it a dollar-figure representation of whether work is ahead or behind the plan. A positive SV indicates work is ahead of schedule; a negative SV indicates work is behind - directly matching the description of comparing earned value of work completed to planned value in dollar terms.

DCost variance

Cost Variance (CV) is calculated as EV minus AC - it compares earned value to actual cost incurred, measuring cost efficiency rather than schedule performance against the plan.

Concept tested: Earned value management - schedule variance formula

Source: https://www.pmi.org/learning/library/earned-value-management-primer-8078

Topics

#earned value management#schedule variance#EV vs PV#EVM metrics