Question
A project manager at a projectized organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date. Which of the following should the project manager do NEXT?
Options
- AAsk the functional manager to release the 20% of allocation from the secondary project.
- BAsk the sponsor to negotiate with the project manager from the secondary project.
- CAsk the PMO to assign additional resources.
- DAsk the project manager of the secondary project to release the resource.