PK0-004 · Question #596
A project manager is informed that the project sponsor was terminated from the project effective immediately. To ensure business continuity, the project manager has been asked to assume additional…
The correct answer is A. Internal reorganization. An internal reorganization occurs when roles, responsibilities, and reporting structures are redistributed within an organization without involving external parties. In this scenario, the sponsor's departure triggers a redistribution of duties to the project manager-both…
Question
A project manager is informed that the project sponsor was terminated from the project effective immediately. To ensure business continuity, the project manager has been asked to assume additional tasks to complete the project on time. Many of these tasks were performed by the former project sponsor. Which of the following types of change does this illustrate?
Options
- AInternal reorganization
- BBusiness demerger
- COutsourcing
- DBusiness process change
How the community answered
(31 responses)- A90% (28)
- B6% (2)
- D3% (1)
Explanation
An internal reorganization occurs when roles, responsibilities, and reporting structures are redistributed within an organization without involving external parties. In this scenario, the sponsor's departure triggers a redistribution of duties to the project manager-both individuals are internal to the same organization. This is a classic example of internal reorganization driven by a personnel change. A business demerger (B) involves splitting one company into two separate entities. Outsourcing (C) involves transferring work to an external vendor or third party. A business process change (D) refers to modifying how a business operation is performed, not who performs it. The key indicator here is that internal roles and responsibilities shifted within the existing organizational structure.
Topics