The burn rate of a project can be described as:
Options
- Ahow quickly a team completes a sprint in the Agile process.
- Bthe amount of time it takes to complete a milestone,
- Cthe rate at which authorized hours or budget is being used.
- Dthe period of time covered under the warranty of a solution.