PK0-004 · Question #588
A project manager is developing a risk management plan and has decided to score each risk based on composite score of impact and probability. In discussions with the project sponsor, they determined…
The correct answer is D. 4 F. 6. They have a composite risk score of lower than 1. Every other risk is higher than 1.
Project management concepts
Question
A project manager is developing a risk management plan and has decided to score each risk based on composite score of impact and probability. In discussions with the project sponsor, they determined that all risks with a composite score lower than 1 will not receive further attention. Which of the following risks should the project manager accept? (Choose two.)
Exhibits
Options
- A1
- B2
- C3
- D4
- E5
- F6
How the community answered
(25 responses)- A4% (1)
- B4% (1)
- C8% (2)
- D84% (21)
Explanation
They have a composite risk score of lower than 1. Every other risk is higher than 1.
Topics
#risk scoring#risk acceptance#composite score#qualitative risk analysis