nerdexam
ExamsPK0-004Questions#588
CompTIA

PK0-004 · Question #588

PK0-004 Question #588: Real Exam Question with Answer & Explanation

The correct answer is D: 4. They have a composite risk score of lower than 1. Every other risk is higher than 1.

Question

A project manager is developing a risk management plan and has decided to score each risk based on composite score of impact and probability. In discussions with the project sponsor, they determined that all risks with a composite score lower than 1 will not receive further attention. Which of the following risks should the project manager accept? (Choose two.)

Exhibit

PK0-004 question #588 exhibit

Options

  • A1
  • B2
  • C3
  • D4
  • E5
  • F6

Explanation

They have a composite risk score of lower than 1. Every other risk is higher than 1.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice