The correct answer is D: 4. They have a composite risk score of lower than 1. Every other risk is higher than 1.
Question
A project manager is developing a risk management plan and has decided to score each risk based on composite score of impact and probability. In discussions with the project sponsor, they determined that all risks with a composite score lower than 1 will not receive further attention. Which of the following risks should the project manager accept? (Choose two.)
Exhibit
Options
- A1
- B2
- C3
- D4
- E5
- F6
Explanation
They have a composite risk score of lower than 1. Every other risk is higher than 1.