Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer. Which of the following is the MOST…

The correct answer is A. The cost will increase. Any type of rework should increase the cost.

Project management concepts

Question

Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer. Which of the following is the MOST likely impact to Project B?

Options

  • AThe cost will increase.
  • BThere will be no impact.
  • CThe scope will change.
  • DThe schedule will change.

How the community answered

(34 responses)
  • A
    56% (19)
  • B
    6% (2)
  • C
    12% (4)
  • D
    26% (9)

Explanation

Any type of rework should increase the cost.