CompTIA
PK0-004 · Question #587
Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer. Which of the following is the MOST…
The correct answer is A. The cost will increase. Any type of rework should increase the cost.
Project management concepts
Question
Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer. Which of the following is the MOST likely impact to Project B?
Options
- AThe cost will increase.
- BThere will be no impact.
- CThe scope will change.
- DThe schedule will change.
How the community answered
(34 responses)- A56% (19)
- B6% (2)
- C12% (4)
- D26% (9)
Explanation
Any type of rework should increase the cost.
Topics
#project dependencies#schedule buffer#regulatory changes#cost impact
Community Discussion
No community discussion yet for this question.