PK0-004 · Question #586
Which of the following project management roles is responsible for estimating the duration of tasks?
The correct answer is C. Project manager. https://activecollab.com/blog/project-management/project-manager-roles-and-responsibilities
Project management concepts
Question
Which of the following project management roles is responsible for estimating the duration of tasks?
Options
- AProject scheduler
- BProject team
- CProject manager
- DProject coordinator
How the community answered
(50 responses)- A2% (1)
- B8% (4)
- C86% (43)
- D4% (2)
Explanation
https://activecollab.com/blog/project-management/project-manager-roles-and-responsibilities
Topics
#project manager role#task duration estimation#roles and responsibilities