PK0-004 · Question #584
A project stakeholder approaches the project manager and wishes to know how long the vendor will provide support for the application being developed for the project. This information should be…
The correct answer is B. kickoff meeting. The commitment of project-specific SLA would be carried out during the project kick-off meeting. This is when the project team would explain their SLA needs and negotiate the SLA from each support department. This allows the project team to have SLAs tailored to meet specific…
Question
A project stakeholder approaches the project manager and wishes to know how long the vendor will provide support for the application being developed for the project. This information should be provided during the:
Options
- Aclosure meeting.
- Bkickoff meeting.
- Cstand-up meeting.
- Dteam meeting.
How the community answered
(22 responses)- A5% (1)
- B91% (20)
- C5% (1)
Explanation
The commitment of project-specific SLA would be carried out during the project kick-off meeting. This is when the project team would explain their SLA needs and negotiate the SLA from each support department. This allows the project team to have SLAs tailored to meet specific needs and project execution becomes predictable.