PK0-004 · Question #582
Which of the following documents is a snapshot in time of a project during the execution phase?
The correct answer is C. Status report. A status report is produced at regular intervals during project execution and captures the project's current state at that specific point in time - progress to date, schedule variance, budget burn, open issues, and risks. It is by definition a time-bound snapshot. The scope…
Question
Which of the following documents is a snapshot in time of a project during the execution phase?
Options
- AScope document
- BPerformance indicators
- CStatus report
- DRisk register
How the community answered
(28 responses)- A4% (1)
- C93% (26)
- D4% (1)
Explanation
A status report is produced at regular intervals during project execution and captures the project's current state at that specific point in time - progress to date, schedule variance, budget burn, open issues, and risks. It is by definition a time-bound snapshot. The scope document (A) is established in planning and remains relatively static. The risk register (D) is a living document continuously updated throughout the project. Performance indicators (B) are metrics used for measurement, not a snapshot document. Only the status report is explicitly time-stamped and snapshot-oriented.