nerdexam
ExamsPK0-004Questions#575
CompTIA

PK0-004 · Question #575

PK0-004 Question #575: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-004 to reveal the answer and full explanation for question #575. The question stem and answer options stay visible for context.

Question

A project manager is working on a project, which needs to be delivered within six months. The project sponsor has made it known that the six months is non-negotiable and additional funding can be provided, if required. The project is in the fifth month, and testing is ongoing. The project team has identified a major defect that will take up to one month to rectify. Which of the following is the BEST action for the project manager to take to ensure the project finishes as planned?

Options

  • AObtain additional resources to crash the timelines.
  • BContinue the project as is and communicate the imminent one-month delay to the sponsor.
  • CFast-track non-critical-path activities.
  • DDeliver the products to meet the timelines and create an additional phase to address issues.

Unlock PK0-004 to see the answer

You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PK0-004 Practice