PK0-004 · Question #570
A project team member has completed an assigned task on time. After updating the project schedule, which of the following steps should the project manager take NEXT?
The correct answer is D. Notify the team members to begin successor tasks. Once a task is complete and the schedule is updated, the immediate priority is to keep work flowing. In a sequenced schedule, completing a predecessor task enables successor tasks to begin. Notifying those team members immediately prevents idle time and maintains momentum…
Question
A project team member has completed an assigned task on time. After updating the project schedule, which of the following steps should the project manager take NEXT?
Options
- ASend an updated schedule to the CCB.
- BSend a project status update to the sponsor.
- CRelease the team members to the functional manager.
- DNotify the team members to begin successor tasks.
How the community answered
(24 responses)- A8% (2)
- B13% (3)
- C4% (1)
- D75% (18)
Explanation
Once a task is complete and the schedule is updated, the immediate priority is to keep work flowing. In a sequenced schedule, completing a predecessor task enables successor tasks to begin. Notifying those team members immediately prevents idle time and maintains momentum. Sending updates to the sponsor (B) or CCB (A) is not required for routine task completion, and releasing team members to the functional manager (C) is premature - the project is still in execution.
Topics
Community Discussion
No community discussion yet for this question.