PK0-004 · Question #555
A highly skilled project engineer will be on indefinite medical leave. No one on the project team has the required skill set to replace the engineer. Which of the following will be impacted MOST by…
The correct answer is A. Resources. When a uniquely skilled team member goes on indefinite medical leave with no available replacement, the most direct and immediate impact is on resources - specifically human resources. The project now has a gap in its resource pool that cannot be filled with existing personnel…
Question
A highly skilled project engineer will be on indefinite medical leave. No one on the project team has the required skill set to replace the engineer. Which of the following will be impacted MOST by the absence of the engineer?
Options
- AResources
- BEnvironment
- CDeliverables
- DRequirements
How the community answered
(45 responses)- A76% (34)
- B4% (2)
- C13% (6)
- D7% (3)
Explanation
When a uniquely skilled team member goes on indefinite medical leave with no available replacement, the most direct and immediate impact is on resources - specifically human resources. The project now has a gap in its resource pool that cannot be filled with existing personnel. While deliverables (C) may eventually be impacted as a downstream consequence, the root constraint is the resource shortage. Requirements (D) and the environment (B) are not directly affected by one person's absence. Resource management - identifying, acquiring, and managing the people needed - is the primary concern here.
Topics
Community Discussion
No community discussion yet for this question.