nerdexam
CompTIA

PK0-004 · Question #554

Which of the following is the BEST reason to conduct regular risk reviews?

The correct answer is B. Risk reviews allow for the identification of response strategies. The primary purpose of regular risk reviews is to identify response strategies - both for newly identified risks and for updating strategies on existing ones as circumstances evolve. Risk reviews keep the risk register current, reassess probabilities and impacts, and ensure…

Project management concepts

Question

Which of the following is the BEST reason to conduct regular risk reviews?

Options

  • ARisk reviews ensure stakeholders take action on assigned items.
  • BRisk reviews allow for the identification of response strategies.
  • CRisk reviews can keep personnel on track with their assigned tasks.
  • DRisk reviews must be reported in status updates.

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    90% (35)
  • C
    3% (1)
  • D
    5% (2)

Explanation

The primary purpose of regular risk reviews is to identify response strategies - both for newly identified risks and for updating strategies on existing ones as circumstances evolve. Risk reviews keep the risk register current, reassess probabilities and impacts, and ensure mitigation, avoidance, transfer, or acceptance plans are in place. Ensuring stakeholders take action on items (A) or keeping personnel on task (C) are project management activities, not the core goal of risk reviews. Reporting in status updates (D) may happen after a risk review but is not the reason to conduct one.

Topics

#risk management#risk review#risk response strategies#risk identification

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice