PK0-004 · Question #554
Which of the following is the BEST reason to conduct regular risk reviews?
The correct answer is B. Risk reviews allow for the identification of response strategies. The primary purpose of regular risk reviews is to identify response strategies - both for newly identified risks and for updating strategies on existing ones as circumstances evolve. Risk reviews keep the risk register current, reassess probabilities and impacts, and ensure…
Question
Which of the following is the BEST reason to conduct regular risk reviews?
Options
- ARisk reviews ensure stakeholders take action on assigned items.
- BRisk reviews allow for the identification of response strategies.
- CRisk reviews can keep personnel on track with their assigned tasks.
- DRisk reviews must be reported in status updates.
How the community answered
(39 responses)- A3% (1)
- B90% (35)
- C3% (1)
- D5% (2)
Explanation
The primary purpose of regular risk reviews is to identify response strategies - both for newly identified risks and for updating strategies on existing ones as circumstances evolve. Risk reviews keep the risk register current, reassess probabilities and impacts, and ensure mitigation, avoidance, transfer, or acceptance plans are in place. Ensuring stakeholders take action on items (A) or keeping personnel on task (C) are project management activities, not the core goal of risk reviews. Reporting in status updates (D) may happen after a risk review but is not the reason to conduct one.