A project is running behind schedule. To meet the delivery timelines, the project manager decides to give part of the work to another organization for quicker delivery and to allow the project team…

The correct answer is B. outsourcing. Outsourcing occurs when an organization uses external resources to perform business processes and tasks. Outsourcing usually involves hiring outside companies to perform business functions or tasks such as payroll, information technology, security, janitorial services, and so…

Project management concepts

Question

A project is running behind schedule. To meet the delivery timelines, the project manager decides to give part of the work to another organization for quicker delivery and to allow the project team to focus on the remaining tasks. This is an example of:

Options

  • Acrashing.
  • Boutsourcing.
  • Ctask reassignment.
  • Drelocation.

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    89% (34)
  • C
    5% (2)
  • D
    3% (1)

Explanation

Outsourcing occurs when an organization uses external resources to perform business processes and tasks. Outsourcing usually involves hiring outside companies to perform business functions or tasks such as payroll, information technology, security, janitorial services, and so on. Outsourcing project team members, for example, by bringing in consultants to help with the work, can alter the make-up of the team. You should watch for team cohesiveness when there are outside members and make certain to nip conflicts before they arise.

Topics

#outsourcing#schedule compression#resource management#vendor management