nerdexam
CompTIA

PK0-004 · Question #556

A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts. Which of the following is MOST likely the cause?

The correct answer is B. The PMO was not involved in project initiation and planning. When the PMO (Project Management Office) is not involved in project initiation and planning, the project lacks proper governance, standardized processes, and oversight frameworks. The PMO ensures that stakeholder identification, scope definition, and planning rigor meet…

Project management concepts

Question

A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts. Which of the following is MOST likely the cause?

Options

  • AThere were not enough resources assigned to the project execution team.
  • BThe PMO was not involved in project initiation and planning.
  • CProper team-building activities were not performed when starting the project.
  • DA few major stakeholders were overlooked during project initiation and planning.

How the community answered

(38 responses)
  • A
    24% (9)
  • B
    55% (21)
  • C
    13% (5)
  • D
    8% (3)

Explanation

When the PMO (Project Management Office) is not involved in project initiation and planning, the project lacks proper governance, standardized processes, and oversight frameworks. The PMO ensures that stakeholder identification, scope definition, and planning rigor meet organizational standards. Without this involvement, critical stakeholders may be overlooked, requirements may be poorly captured, and planning may be inadequate - all of which directly cause requirement conflicts, rework, schedule delays, and budget overruns. While overlooked stakeholders (D) is a symptom, the root cause is the absence of PMO governance that would have prevented it.

Topics

#stakeholder management#project initiation#PMO involvement#requirements management

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice