Question
A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts. Which of the following is MOST likely the cause?
Options
- AThere were not enough resources assigned to the project execution team.
- BThe PMO was not involved in project initiation and planning.
- CProper team-building activities were not performed when starting the project.
- DA few major stakeholders were overlooked during project initiation and planning.