Which of the following events would MOST likely merit immediate communication to all project stakeholders? (Choose two.)

The correct answer is A. Business continuity response B. Milestone achievement. Business continuity response (A) and incident response (C) are unplanned, urgent events that can significantly disrupt the project and require immediate communication to all stakeholders so they can take appropriate action. Milestone achievement (B) is noteworthy but is a…

Project management concepts

Question

Which of the following events would MOST likely merit immediate communication to all project stakeholders? (Choose two.)

Options

  • ABusiness continuity response
  • BMilestone achievement
  • CIncident response
  • DSchedule change
  • EChange request
  • FStakeholder changes

How the community answered

(34 responses)
  • A
    91% (31)
  • E
    3% (1)
  • F
    6% (2)

Explanation

Business continuity response (A) and incident response (C) are unplanned, urgent events that can significantly disrupt the project and require immediate communication to all stakeholders so they can take appropriate action. Milestone achievement (B) is noteworthy but is a planned, positive event that follows regular reporting cadences rather than triggering emergency-level communication. Schedule changes (D), change requests (E), and stakeholder changes (F) are typically handled through standard communication channels and change management processes, not immediate all-stakeholder alerts.

Topics

#communication triggers#stakeholder communication#milestone#incident response