PK0-004 · Question #546
A developer is experiencing constant project scope changes and reaches out to the project manager to discuss the situation. They agree the customer has requested multiple modifications to the core…
The correct answer is A. Strict change management controls. When a customer is continuously requesting scope changes, strict change management controls are the best defense against scope creep. A formal change control process ensures every modification is documented, evaluated for schedule and cost impact, and approved before work…
Question
A developer is experiencing constant project scope changes and reaches out to the project manager to discuss the situation. They agree the customer has requested multiple modifications to the core idea and now extra work may need to be performed. Which of the following approaches would BEST support on- time delivery considering these changes?
Options
- AStrict change management controls
- BRegular Scrum meetings
- CContinuous requirements gathering
- DRegular milestone reviews
How the community answered
(38 responses)- A74% (28)
- B8% (3)
- C3% (1)
- D16% (6)
Explanation
When a customer is continuously requesting scope changes, strict change management controls are the best defense against scope creep. A formal change control process ensures every modification is documented, evaluated for schedule and cost impact, and approved before work begins. This prevents uncontrolled expansion of scope that would threaten on-time delivery. Regular Scrum meetings (B) facilitate communication but don't control scope. Continuous requirements gathering (C) actually encourages more changes. Milestone reviews (D) monitor progress but don't prevent scope changes.
Topics
Community Discussion
No community discussion yet for this question.