A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?
The correct answer is B. Communicate the success to the team. When a task finishes ahead of schedule, the most appropriate immediate step is to communicate the success to the team. This maintains transparency, boosts morale, and ensures everyone is aware of the current project state. Assigning the next task (A) should only occur after the…
Question
A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?
Options
- AProvide the next task to the newly freed resource.
- BCommunicate the success to the team.
- CNotify the project sponsor of the new completion date.
- DUpdate the schedule and add lag to the next task.
How the community answered
(26 responses)- A4% (1)
- B92% (24)
- C4% (1)
Explanation
When a task finishes ahead of schedule, the most appropriate immediate step is to communicate the success to the team. This maintains transparency, boosts morale, and ensures everyone is aware of the current project state. Assigning the next task (A) should only occur after the project manager reviews the schedule and resource plan - not spontaneously. Notifying the sponsor of a new completion date (C) is premature based on a single task. Adding lag to the next task (D) is counterproductive and could artificially slow the project down.
Topics