During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to…
The correct answer is A. 12 days. Calculate the durations separately following the dependencies, The critical task is the longest tasks duration not the longest duration of the project as a whole.
Tools and documentation
Question
During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
Exhibits
Options
- A12 days
- B14 days
- C16 days
- D19 days
How the community answered
(50 responses)- A62% (31)
- B4% (2)
- C22% (11)
- D12% (6)
Explanation
Calculate the durations separately following the dependencies, The critical task is the longest tasks duration not the longest duration of the project as a whole.
Topics
#critical path#schedule recalculation#task duration#network diagram