nerdexam
ExamsPK0-004Questions#52
CompTIA

PK0-004 · Question #52

PK0-004 Question #52: Real Exam Question with Answer & Explanation

The correct answer is A: 12 days. Calculate the durations separately following the dependencies, The critical task is the longest tasks duration not the longest duration of the project as a whole.

Question

During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

Exhibit

PK0-004 question #52 exhibit

Options

  • A12 days
  • B14 days
  • C16 days
  • D19 days

Explanation

Calculate the durations separately following the dependencies, The critical task is the longest tasks duration not the longest duration of the project as a whole.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice