nerdexam
CompTIA

PK0-004 · Question #52

During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to…

The correct answer is A. 12 days. Calculate the durations separately following the dependencies, The critical task is the longest tasks duration not the longest duration of the project as a whole.

Tools and documentation

Question

During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

Exhibits

PK0-004 question #52 exhibit 1
PK0-004 question #52 exhibit 2
PK0-004 question #52 exhibit 3

Options

  • A12 days
  • B14 days
  • C16 days
  • D19 days

How the community answered

(50 responses)
  • A
    62% (31)
  • B
    4% (2)
  • C
    22% (11)
  • D
    12% (6)

Explanation

Calculate the durations separately following the dependencies, The critical task is the longest tasks duration not the longest duration of the project as a whole.

Topics

#critical path#schedule recalculation#task duration#network diagram

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice