CompTIA
PK0-004 · Question #52
PK0-004 Question #52: Real Exam Question with Answer & Explanation
The correct answer is A: 12 days. Calculate the durations separately following the dependencies, The critical task is the longest tasks duration not the longest duration of the project as a whole.
Question
During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
Exhibit
Options
- A12 days
- B14 days
- C16 days
- D19 days
Explanation
Calculate the durations separately following the dependencies, The critical task is the longest tasks duration not the longest duration of the project as a whole.
Community Discussion
No community discussion yet for this question.
