Question
During planning, a project coordinator publishes the project management plan. After reviewing the plan, the project sponsor is concerned it is too long and detailed. Which of the following does the project sponsor desire?
Options
- AStatus report
- BTask durations
- CProject schedule
- DSchedule management plan