PK0-004 · Question #513
During planning, a project coordinator publishes the project management plan. After reviewing the plan, the project sponsor is concerned it is too long and detailed. Which of the following does the…
The correct answer is C. Project schedule. The purpose of the project schedule is to coordinate activities to form a master plan in order to complete the project objectives on time. It is also used to track schedule performance and keep upper management and project stakeholders informed about the project's status.
Question
During planning, a project coordinator publishes the project management plan. After reviewing the plan, the project sponsor is concerned it is too long and detailed. Which of the following does the project sponsor desire?
Options
- AStatus report
- BTask durations
- CProject schedule
- DSchedule management plan
How the community answered
(38 responses)- A5% (2)
- B11% (4)
- C82% (31)
- D3% (1)
Explanation
The purpose of the project schedule is to coordinate activities to form a master plan in order to complete the project objectives on time. It is also used to track schedule performance and keep upper management and project stakeholders informed about the project's status.