PK0-004 · Question #477
A project team received a memo stating no one can come into the office for the rest of the week due to heavy forecasted rain. The projected team reviews the risk management plan and carries out the…
The correct answer is D. risk trigger. A risk trigger (also called a risk symptom or warning sign) is an event or condition that indicates a risk is about to occur or has occurred, prompting the activation of a planned risk response. In this scenario, the memo about forecasted heavy rain is the signal that activates…
Question
A project team received a memo stating no one can come into the office for the rest of the week due to heavy forecasted rain. The projected team reviews the risk management plan and carries out the risk response. The memo that prompted the activation of the risk response is referred to as the:
Options
- Arisk owner
- Brisk impact
- Crisk review
- Drisk trigger
How the community answered
(35 responses)- A6% (2)
- C3% (1)
- D91% (32)
Explanation
A risk trigger (also called a risk symptom or warning sign) is an event or condition that indicates a risk is about to occur or has occurred, prompting the activation of a planned risk response. In this scenario, the memo about forecasted heavy rain is the signal that activates the team's pre-planned response. A risk owner (A) is the person responsible for managing a specific risk. Risk impact (B) refers to the potential consequences if the risk occurs. A risk review (C) is a periodic reassessment of the risk register-none of these describe the activating event itself.
Topics
Community Discussion
No community discussion yet for this question.