nerdexam
ExamsPK0-004Questions#478
CompTIA

PK0-004 · Question #478

PK0-004 Question #478: Real Exam Question with Answer & Explanation

The correct answer is A: Project manager. When a WBS task is completed, the two primary recipients of that notification are the project manager (A) and the project scheduler (E). The project manager needs to know to update overall project status, manage dependencies, and communicate progress to stakeholders. The project

Question

When a project team member completes a task in the WBS, which of the following are the primary recipients of the notification? (Choose two.)

Options

  • AProject manager
  • BProject sponsor
  • CKey stakeholder
  • DHuman resources
  • EProject scheduler
  • FProject management office

Explanation

When a WBS task is completed, the two primary recipients of that notification are the project manager (A) and the project scheduler (E). The project manager needs to know to update overall project status, manage dependencies, and communicate progress to stakeholders. The project scheduler needs the completion data to update the project schedule, adjust remaining timelines, and ensure successor tasks can begin. The project sponsor (B) receives high-level milestone updates, not individual task completions. Key stakeholders (C), HR (D), and the PMO (F) are not routine recipients of individual task completion notices.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice