PK0-004 · Question #478
When a project team member completes a task in the WBS, which of the following are the primary recipients of the notification? (Choose two.)
The correct answer is A. Project manager E. Project scheduler. When a WBS task is completed, the two primary recipients of that notification are the project manager (A) and the project scheduler (E). The project manager needs to know to update overall project status, manage dependencies, and communicate progress to stakeholders. The…
Question
When a project team member completes a task in the WBS, which of the following are the primary recipients of the notification? (Choose two.)
Options
- AProject manager
- BProject sponsor
- CKey stakeholder
- DHuman resources
- EProject scheduler
- FProject management office
How the community answered
(39 responses)- A90% (35)
- B3% (1)
- D3% (1)
- F5% (2)
Explanation
When a WBS task is completed, the two primary recipients of that notification are the project manager (A) and the project scheduler (E). The project manager needs to know to update overall project status, manage dependencies, and communicate progress to stakeholders. The project scheduler needs the completion data to update the project schedule, adjust remaining timelines, and ensure successor tasks can begin. The project sponsor (B) receives high-level milestone updates, not individual task completions. Key stakeholders (C), HR (D), and the PMO (F) are not routine recipients of individual task completion notices.
Topics
Community Discussion
No community discussion yet for this question.