PK0-004 · Question #459
Risk ID 2 has occurred. Which of the following ways should the project manager update the risk register?
The correct answer is C. Change the risk 2 status to issue. When a risk event actually occurs, it transitions from a potential risk into an active problem - formally called an issue. The correct update is to change the risk's status to 'issue' (C) in the risk register. This signals that the risk is no longer hypothetical and requires…
Question
Risk ID 2 has occurred. Which of the following ways should the project manager update the risk register?
Options
- AAdd a column for probability and set risk 2 at 100%
- BChange the risk 2 response to backups restored
- CChange the risk 2 status to issue
- DChange the risk 2 owner to PM
How the community answered
(26 responses)- A4% (1)
- B4% (1)
- C85% (22)
- D8% (2)
Explanation
When a risk event actually occurs, it transitions from a potential risk into an active problem - formally called an issue. The correct update is to change the risk's status to 'issue' (C) in the risk register. This signals that the risk is no longer hypothetical and requires immediate action. Setting probability to 100% (A) is technically accurate but not standard practice for a realized risk. Changing the response to 'backups restored' (B) describes a resolution action, not a status update. Reassigning ownership to the PM (D) may or may not be appropriate but is not the standard first update step.