PK0-004 · Question #451
There is a project in which the team can only meet once every three months. When the team does meet, no one can remember what was discussed and decided upon last time; thus, progress is being…
The correct answer is D. Meeting minutes. Meeting minutes are a formal record of what was discussed, decided, and assigned during a meeting, including action items and owners. With infrequent meetings, having documented minutes from the previous session ensures continuity and accountability-team members can review what…
Question
There is a project in which the team can only meet once every three months. When the team does meet, no one can remember what was discussed and decided upon last time; thus, progress is being delayed. Which of the following project management tools would help?
Options
- AIssue log
- BProject charter
- CDashboard
- DMeeting minutes
How the community answered
(50 responses)- A2% (1)
- B4% (2)
- C2% (1)
- D92% (46)
Explanation
Meeting minutes are a formal record of what was discussed, decided, and assigned during a meeting, including action items and owners. With infrequent meetings, having documented minutes from the previous session ensures continuity and accountability-team members can review what was agreed upon before the next meeting. An issue log tracks open issues, a project charter defines project authorization and high-level scope, and a dashboard shows current status metrics. None of those address the problem of failing to recall prior meeting decisions.