A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval. Which…

The correct answer is D. Change implementation. The Change Control Board (CCB) must approve changes before they are implemented. If modifications were deployed prior to CCB approval, the breakdown occurred in the Change Implementation step - meaning someone executed the change without waiting for the required authorization…

Project management concepts

Question

A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval. Which of the following change control processes is being mismanaged?

Options

  • AChange validation with quality checks
  • BRegression planning
  • CIdentify approval authority
  • DChange implementation

How the community answered

(16 responses)
  • A
    6% (1)
  • B
    25% (4)
  • C
    6% (1)
  • D
    63% (10)

Explanation

The Change Control Board (CCB) must approve changes before they are implemented. If modifications were deployed prior to CCB approval, the breakdown occurred in the Change Implementation step - meaning someone executed the change without waiting for the required authorization. Change validation with quality checks (A) happens after implementation. Regression planning (B) is a testing concern. Identifying the approval authority (C) relates to knowing who must approve, but the CCB clearly existed here; the problem is that the team bypassed the approval and went straight to deployment, which is a failure in the implementation step of the change control process.

Topics

#change control board#CCB approval#change implementation#change management