A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively…

The correct answer is C. Project sponsor. The sponsor has a high level of authority in general over the project.

Project management concepts

Question

A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling. Which of the following resources has the authority to authorize this change?

Options

  • AStakeholders
  • BScrum master
  • CProject sponsor
  • DProject team

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    80% (24)
  • D
    13% (4)

Explanation

The sponsor has a high level of authority in general over the project.

Topics

#change authority#project sponsor#scheduling conflict#stakeholder roles