Which of the following project phases occurs when requirements are detailed?
The correct answer is C. Planning. Requirements are detailed during the Planning phase. This is where the project team elaborates on the high-level scope identified during initiation, breaking it down into specific, measurable, and documented requirements. Initiation (A) captures high-level goals and…
Question
Which of the following project phases occurs when requirements are detailed?
Options
- AInitiation
- BMonitor and control
- CPlanning
- DClosing
How the community answered
(40 responses)- A5% (2)
- B3% (1)
- C93% (37)
Explanation
Requirements are detailed during the Planning phase. This is where the project team elaborates on the high-level scope identified during initiation, breaking it down into specific, measurable, and documented requirements. Initiation (A) captures high-level goals and feasibility, not detailed requirements. Monitor and Control (B) is an ongoing process group that tracks performance against the plan - it does not define requirements. Closing (D) involves finalizing deliverables and formally ending the project. Planning is the phase dedicated to defining scope, developing the WBS, and documenting detailed requirements.
Topics
Community Discussion
No community discussion yet for this question.