PK0-004 · Question #410

Which of the following project phases occurs when requirements are detailed?

The correct answer is C. Planning. Requirements are detailed during the Planning phase. This is where the project team elaborates on the high-level scope identified during initiation, breaking it down into specific, measurable, and documented requirements. Initiation (A) captures high-level goals and…

Project life cycle phases

Question

Which of the following project phases occurs when requirements are detailed?

Options

  • AInitiation
  • BMonitor and control
  • CPlanning
  • DClosing

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    93% (37)

Explanation

Requirements are detailed during the Planning phase. This is where the project team elaborates on the high-level scope identified during initiation, breaking it down into specific, measurable, and documented requirements. Initiation (A) captures high-level goals and feasibility, not detailed requirements. Monitor and Control (B) is an ongoing process group that tracks performance against the plan - it does not define requirements. Closing (D) involves finalizing deliverables and formally ending the project. Planning is the phase dedicated to defining scope, developing the WBS, and documenting detailed requirements.

Topics

#planning phase#requirements definition#project phases#scope planning