PK0-004 · Question #404
PK0-004 Question #404: Real Exam Question with Answer & Explanation
The correct answer is D: Critical path method. The Critical Path Method (CPM) is a deterministic scheduling technique that focuses on the duration of each activity to identify the longest path through the project network (the critical path) and calculate float/slack for all non-critical activities. PERT (A) uses probabilistic
Question
Options
- AProgram evaluation review technique
- BPrecedence diagramming method
- CArrow diagramming method
- DCritical path method
Explanation
The Critical Path Method (CPM) is a deterministic scheduling technique that focuses on the duration of each activity to identify the longest path through the project network (the critical path) and calculate float/slack for all non-critical activities. PERT (A) uses probabilistic time estimates (optimistic, pessimistic, most likely) to handle uncertainty. The Precedence Diagramming Method (B) defines logical relationships between tasks (Finish-to-Start, Start-to-Start, etc.). The Arrow Diagramming Method (C) uses arrows to represent activities. CPM is specifically designed around duration analysis and slack calculation.
Community Discussion
No community discussion yet for this question.