PK0-004 · Question #274
A project scope document would include which of the following? (Select TWO).
The correct answer is B. Key performance indicators C. Assumptions. A project scope document defines what is and is not included in the project, and typically contains KPIs and documented assumptions alongside deliverables and constraints.
Question
A project scope document would include which of the following? (Select TWO).
Options
- AWBS
- BKey performance indicators
- CAssumptions
- DRisk matrix
- ENetwork diagram
How the community answered
(37 responses)- A5% (2)
- B92% (34)
- E3% (1)
Why each option
A project scope document defines what is and is not included in the project, and typically contains KPIs and documented assumptions alongside deliverables and constraints.
The WBS is a separate planning artifact created from the scope statement - it is not contained within the scope document itself.
Key performance indicators (KPIs) are included in the scope document to define measurable criteria for evaluating project success and deliverable quality. Assumptions document conditions believed to be true for planning purposes and are a standard component of the project scope statement per PMBOK guidance.
Assumptions are explicitly listed in the project scope statement to capture conditions that are accepted as true without proof, which directly affect how scope is defined and managed.
A risk matrix is part of the risk management plan or risk register, not the scope document.
A network diagram is a scheduling tool used in time management, not a component of the project scope document.
Concept tested: Project scope document standard components
Source: https://www.pmi.org/learning/library/project-scope-statement-development-7129
Topics
Community Discussion
No community discussion yet for this question.