CompTIA
PK0-004 · Question #270
PK0-004 Question #270: Real Exam Question with Answer & Explanation
The correct answer is B: At the end of the project to transfer maintenance responsibilities. A transition plan is used at the end of a project to formally hand off deliverables and transfer maintenance responsibilities to the operational or support team.
Question
In which of the following areas would a transition plan be used?
Options
- AAs a project phase is completed and the project shifts to a new phase
- BAt the end of the project to transfer maintenance responsibilities
- CAfter the project receives approval and becomes an active project
- DWhen the project manager is added to the project and the project authority shifts to their
Explanation
A transition plan is used at the end of a project to formally hand off deliverables and transfer maintenance responsibilities to the operational or support team.
Common mistakes.
- A. Moving between project phases is governed by phase gates or stage gate reviews, not a transition plan, which is specifically focused on the end-of-project handoff to operations.
- C. Project approval converts a proposal into an active project and is documented in the project charter or approval record, not in a transition plan.
- D. Adding a project manager and shifting authority is addressed through the project charter or responsibility assignment matrix, not through a transition plan.
Concept tested. Transition plan purpose at project closure
Community Discussion
No community discussion yet for this question.