nerdexam
ExamsPK0-004Questions#270
CompTIA

PK0-004 · Question #270

PK0-004 Question #270: Real Exam Question with Answer & Explanation

The correct answer is B: At the end of the project to transfer maintenance responsibilities. A transition plan is used at the end of a project to formally hand off deliverables and transfer maintenance responsibilities to the operational or support team.

Question

In which of the following areas would a transition plan be used?

Options

  • AAs a project phase is completed and the project shifts to a new phase
  • BAt the end of the project to transfer maintenance responsibilities
  • CAfter the project receives approval and becomes an active project
  • DWhen the project manager is added to the project and the project authority shifts to their

Explanation

A transition plan is used at the end of a project to formally hand off deliverables and transfer maintenance responsibilities to the operational or support team.

Common mistakes.

  • A. Moving between project phases is governed by phase gates or stage gate reviews, not a transition plan, which is specifically focused on the end-of-project handoff to operations.
  • C. Project approval converts a proposal into an active project and is documented in the project charter or approval record, not in a transition plan.
  • D. Adding a project manager and shifting authority is addressed through the project charter or responsibility assignment matrix, not through a transition plan.

Concept tested. Transition plan purpose at project closure

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice