The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes. Which of the following best describes what the PM…

The correct answer is C. Meeting agenda. A fishbone diagram is a cause-and-effect diagram that shows the relationship between the effects of problems and their causes. This diagram depicts every potential cause of a problem and the effect that each proposed solution will have on the problem.

Project life cycle phases

Question

The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes. Which of the following best describes what the PM should work on FIRST?

Options

  • AProject charter
  • BProject schedule
  • CMeeting agenda
  • DResponsibility assignment matrix
  • ERisk register

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    87% (41)
  • E
    2% (1)

Explanation

A fishbone diagram is a cause-and-effect diagram that shows the relationship between the effects of problems and their causes. This diagram depicts every potential cause of a problem and the effect that each proposed solution will have on the problem.