PK0-004 · Question #1035
Work, tasks, and resources have been identified. In which of the following should this be captured?
The correct answer is C. Schedule in the planning phase. The project schedule, developed during the planning phase, is where work, tasks, and resources are formally captured and organized. The schedule defines what work needs to be done, breaks it into tasks, assigns resources to those tasks, and establishes timelines. The project…
Question
Work, tasks, and resources have been identified. In which of the following should this be captured?
Options
- ACharter in the initiation phase
- BBudget in the planning phase
- CSchedule in the planning phase
- DDeliverables in the execution phase
How the community answered
(28 responses)- A4% (1)
- C93% (26)
- D4% (1)
Explanation
The project schedule, developed during the planning phase, is where work, tasks, and resources are formally captured and organized. The schedule defines what work needs to be done, breaks it into tasks, assigns resources to those tasks, and establishes timelines. The project charter (A) is high-level and created during initiation. The budget (B) captures costs, not tasks or work assignments. Deliverables (D) are outputs produced during execution, not the place where tasks and resources are defined.
Topics
Community Discussion
No community discussion yet for this question.