PK0-004 · Question #1033

PK0-004 Question #1033: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-004 to reveal the answer and full explanation for question #1033. The question stem and answer options stay visible for context.

Question

During a meeting, a key stakeholder hears about a new project and immediately demands the sponsor provide weekly progress reports. The project manager quickly informs the sponsor that the stakeholder does not need a weekly report. Which of the following explains how the project manager reached this conclusion?

Options

  • AThe project manager reviewed the stakeholder register.
  • BThe project charter does not provide the stakeholder with authority.
  • CThe stakeholder is not on the meeting minute distribution list.
  • DThe project manager reviewed the risk register.

Unlock PK0-004 to see the answer