Question
After the first batch of a product is delivered to quality control, the results are not positive. The project manager conducts an analysis, which concludes there was a design error. Which of the following tools did the project manager MOST likely use for the analysis?
Options
- AHistogram
- BFishbone diagram
- CPareto chart
- DScatter diagram