A key stakeholder reviews the project charter and expresses concern that the milestones are not documented. Which of the following should the project manager do?

The correct answer is B. Add the baselines to the charter after a change request has been approved. The project charter is a formally approved document that authorizes the project and typically includes high-level milestones. If milestones are missing, they should be added - but since the charter is a controlled baseline document, any changes to it must go through the formal…

Project life cycle phases

Question

A key stakeholder reviews the project charter and expresses concern that the milestones are not documented. Which of the following should the project manager do?

Options

  • ADirect the key stakeholder to review the project management plan
  • BAdd the baselines to the charter after a change request has been approved
  • CDocument the key stakeholder's concerns in the issue log
  • DProvide the key stakeholder with a status report to show where the project currently stands

How the community answered

(57 responses)
  • A
    11% (6)
  • B
    82% (47)
  • C
    2% (1)
  • D
    5% (3)

Explanation

The project charter is a formally approved document that authorizes the project and typically includes high-level milestones. If milestones are missing, they should be added - but since the charter is a controlled baseline document, any changes to it must go through the formal change control process first. A change request must be submitted and approved before altering the charter. Directing the stakeholder to the project management plan (A) does not resolve the concern about the charter. Logging the concern (C) without acting is insufficient. Providing a status report (D) addresses current progress, not the missing charter content.

Topics

#project charter#milestones#change request#baselines