PK0-003 · Question #90
In the planning phase of a project, which of the following activities is performed?
The correct answer is C. Appoint a project team. The planning phase involves detailing how the project will be executed, which includes defining roles and responsibilities. Appointing a project team is a key activity within this phase to ensure that the necessary resources are in place to proceed with detailed planning and exec
Question
In the planning phase of a project, which of the following activities is performed?
Options
- ASolicitation
- BPerform a feasibility study
- CAppoint a project team
- DProject Charter
How the community answered
(14 responses)- A7% (1)
- C93% (13)
Why each option
The planning phase involves detailing how the project will be executed, which includes defining roles and responsibilities. Appointing a project team is a key activity within this phase to ensure that the necessary resources are in place to proceed with detailed planning and execution.
Solicitation (e.g., soliciting bids from vendors) typically occurs during the procurement process, which is often part of the execution phase, not strictly the initial planning phase for internal team setup.
Performing a feasibility study typically precedes the formal planning phase, often occurring during the initiation phase or even before, to determine if a project is viable.
Appointing a project team is a crucial activity in the planning phase because it involves assigning specific individuals to roles and responsibilities necessary for executing the project plan. This ensures that the human resources are allocated and organized before detailed work begins.
Creating a Project Charter is a primary output of the project initiation phase, formally authorizing the project and the project manager, before detailed planning begins.
Concept tested: Project planning phase activities