Which of the following strategies would be used to reduce the impact of a risk?

The correct answer is A. Risk mitigation. Risk mitigation is the strategy specifically designed to reduce the probability or impact of a negative risk event. It involves taking actions to lessen the potential harm if a risk occurs.

Project management concepts

Question

Which of the following strategies would be used to reduce the impact of a risk?

Options

  • ARisk mitigation
  • BRisk avoidance
  • CRisk acceptance
  • DRisk transfer

How the community answered

(36 responses)
  • A
    86% (31)
  • B
    3% (1)
  • C
    8% (3)
  • D
    3% (1)

Why each option

Risk mitigation is the strategy specifically designed to reduce the probability or impact of a negative risk event. It involves taking actions to lessen the potential harm if a risk occurs.

ARisk mitigationCorrect

Risk mitigation involves taking proactive steps to reduce the likelihood of a risk occurring or to lessen its potential impact if it does occur. This strategy focuses on implementing controls or countermeasures to keep the risk within acceptable levels.

BRisk avoidance

Risk avoidance is a strategy to eliminate the risk entirely by stopping the activity that causes the risk, not just reducing its impact.

CRisk acceptance

Risk acceptance means deciding to take no action regarding a risk and simply dealing with its consequences if it materializes, rather than reducing its impact.

DRisk transfer

Risk transfer involves shifting the responsibility and potential impact of a risk to a third party, often through insurance or outsourcing, not directly reducing the impact by internal actions.