PK0-003 · Question #60

When evaluating project management risks, which of the following methods is being used if risk identification is difficult and time-consuming?

The correct answer is C. Qualitative analysis. The question asks to identify the risk evaluation method described by difficult and time-consuming risk identification.

Project management concepts

Question

When evaluating project management risks, which of the following methods is being used if risk identification is difficult and time-consuming?

Options

  • AQuantitative analysis
  • BNarrative analysis
  • CQualitative analysis
  • DProbability analysis

How the community answered

(17 responses)
  • B
    6% (1)
  • C
    94% (16)

Why each option

The question asks to identify the risk evaluation method described by difficult and time-consuming risk identification.

AQuantitative analysis

Quantitative risk analysis focuses on numerically analyzing the combined effect of identified risks on overall project objectives using statistical techniques, and while it can be complex, the difficulty and time-consuming aspect is more pronounced in the initial identification and assessment phase of qualitative analysis, which often precedes quantitative.

BNarrative analysis

Narrative analysis is not a standard, recognized method for evaluating project risks in the context of project management methodologies like PMBOK.

CQualitative analysisCorrect

Qualitative risk analysis involves assessing the probability and impact of identified risks using descriptive terms and categories, which can be difficult and time-consuming during the initial identification phase due to the subjective nature of gathering expert opinions and categorizing numerous potential risks without detailed data. This method prioritizes risks for further analysis or response.

DProbability analysis

Probability analysis is a component or technique used within both qualitative and quantitative risk analysis, focusing specifically on assessing the likelihood of a risk occurring, rather than a standalone overarching method for risk evaluation, especially not one primarily characterized by difficult/time-consuming identification.

Concept tested: Qualitative risk analysis characteristics

Topics

#Risk analysis#Qualitative analysis#Risk identification

Community Discussion

No community discussion yet for this question.