PK0-003 · Question #59

The project manager of a project that involves a system-wide computer update receives a report that some computers cannot be updated. Which of the following is a BEST practice?

The correct answer is D. Perform an impact analysis and contact the project sponsor.. This question describes an issue during a project and asks for the best practice a project manager should follow.

Project management concepts

Question

The project manager of a project that involves a system-wide computer update receives a report that some computers cannot be updated. Which of the following is a BEST practice?

Options

  • AContact the stakeholders in the project to determine the best course of action.
  • BComplete a project management change form without notifying the sponsor.
  • CDocument the change to the project without informing the stakeholders.
  • DPerform an impact analysis and contact the project sponsor.

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    16% (4)
  • D
    76% (19)

Why each option

This question describes an issue during a project and asks for the best practice a project manager should follow.

AContact the stakeholders in the project to determine the best course of action.

While contacting stakeholders is important, the best practice is to first understand the impact of the problem yourself (impact analysis) and inform the project sponsor, who has ultimate authority, before broadly consulting all stakeholders on a course of action.

BComplete a project management change form without notifying the sponsor.

Completing a change form without notifying the sponsor is poor communication and governance, as the sponsor needs to be aware of significant issues and approve changes.

CDocument the change to the project without informing the stakeholders.

Documenting the change without informing stakeholders, especially the sponsor, is a critical failure in communication and transparency, which can lead to project failure or lack of support.

DPerform an impact analysis and contact the project sponsor.Correct

When an issue like computers failing to update arises, it represents a deviation from the project plan that requires a formal response. A best practice is to first perform an impact analysis to understand the consequences on scope, schedule, cost, and quality, and then promptly contact the project sponsor to inform them and discuss potential solutions or formal change requests.

Concept tested: Project issue management and change control

Topics

#Issue management#Impact analysis#Stakeholder communication#Project control