PK0-003 · Question #440

A project manager was called into the office of the Chief Information Officer (CIO) and informed that the resource budget for the company has been reduced by 10%. The CIO expects that the project must

The correct answer is B. Quality will be impacted.. Given a reduced budget and a fixed timeline, if the project scope is expected to be maintained, the project's quality will likely be impacted.

Project management concepts

Question

A project manager was called into the office of the Chief Information Officer (CIO) and informed that the resource budget for the company has been reduced by 10%. The CIO expects that the project must be completed on time. Which of the following will be impacted?

Options

  • AProject scope will be impacted.
  • BQuality will be impacted.
  • CWBS will be impacted.
  • DSOW will be impacted.

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    63% (22)
  • C
    23% (8)
  • D
    11% (4)

Why each option

Given a reduced budget and a fixed timeline, if the project scope is expected to be maintained, the project's quality will likely be impacted.

AProject scope will be impacted.

While project scope is often the first variable considered for adjustment when constraints change, the question implies an expectation of project completion within the fixed timeline, making quality the most probable impact if budget is cut and scope must be largely preserved.

BQuality will be impacted.Correct

This scenario illustrates the project management constraint triangle (or triple constraint) of scope, time, and cost/quality. When the budget (cost/resources) is reduced and the timeline (time) remains fixed, and there's an expectation that the project will be completed (implying scope is also maintained), the project manager will most likely need to compromise on the quality of the deliverables to meet the remaining constraints.

CWBS will be impacted.

The Work Breakdown Structure (WBS) decomposes the project's scope into manageable components; while changes to scope would impact the WBS, the primary direct impact of a budget cut with fixed time and implied fixed scope is on quality.

DSOW will be impacted.

The Statement of Work (SOW) defines the project's requirements and deliverables. Similar to scope, while it might be revised under certain conditions, the direct impact of a budget cut when time is fixed and scope is expected is primarily on quality.

Concept tested: Project triple constraint management

Topics

#Triple constraint#Quality impact#Resource constraints#Budget cuts