Question
The project manager has documented a change request from a key project stakeholder. Which of the following actions should the project manager take NEXT?
Options
- ADiscuss this change during the next status meeting.
- BAsk other stakeholders for recommendations.
- CSend the request to the change control board.
- DPerform an impact analysis.