nerdexam
ExamsPK0-003Questions#421
CompTIA

PK0-003 · Question #421

PK0-003 Question #421: Real Exam Question with Answer & Explanation

The correct answer is C: Mitigation. See the full explanation below for the reasoning.

Question

A hurricane is forecasted near the corporations call center. The project manager has arranged for a redundant call center in another location to accept calls if the corporate call center is unable to receive calls. Which of the following risk responses is the project manager using?

Options

  • AAvoidance
  • BAcceptance
  • CMitigation
  • DTransference

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice
A hurricane is forecasted near the corporations call center. The... | PK0-003 Q#421 Answer | NerdExam