PK0-003 · Question #403

Which of the following would be a direct output of the initiating process group? (Select Two).

The correct answer is A. Project charter E. Preliminary scope statement. The initiating process group primarily focuses on defining a new project or a new phase of an existing project, leading to the creation of the project charter and preliminary scope statement. These documents formally authorize the project and outline its initial high-level bounda

Project life cycle phases

Question

Which of the following would be a direct output of the initiating process group? (Select Two).

Options

  • AProject charter
  • BProject management plan
  • CStatement of Work (SOW)
  • DWork Breakdown Structure (WBS)
  • EPreliminary scope statement

How the community answered

(58 responses)
  • A
    86% (50)
  • B
    3% (2)
  • C
    9% (5)
  • D
    2% (1)

Why each option

The initiating process group primarily focuses on defining a new project or a new phase of an existing project, leading to the creation of the project charter and preliminary scope statement. These documents formally authorize the project and outline its initial high-level boundaries.

AProject charterCorrect

The Project Charter is the primary output of the Initiating Process Group, formally authorizing the existence of a project and providing the project manager with the authority to apply organizational resources to project activities.

BProject management plan

The Project Management Plan is developed during the Planning Process Group, integrating and consolidating all subsidiary plans.

CStatement of Work (SOW)

A Statement of Work (SOW) is typically an input to the project initiation process, often provided by the customer or sponsor, describing the products or services to be delivered.

DWork Breakdown Structure (WBS)

The Work Breakdown Structure (WBS) is a key output of the Planning Process Group, specifically created during the Scope Definition process to decompose project deliverables into smaller, more manageable components.

EPreliminary scope statementCorrect

While the Project Charter provides high-level scope, the Preliminary Scope Statement (or high-level project scope description) is also an output of the initiating process, further detailing the project's boundaries, deliverables, and acceptance criteria at a preliminary level.

Concept tested: Project management process groups - Initiating

Topics

#Initiating process group#Project charter#Preliminary scope statement