PK0-003 · Question #279
During which of the following process groups is the project charter developed?
The correct answer is A. Pre-project setup. The project charter is developed during the initiating process group, which typically occurs at the beginning of a project or phase, often referred to as pre-project setup.
Question
During which of the following process groups is the project charter developed?
Options
- APre-project setup
- BProject execution
- CProject planning
- DProject control
How the community answered
(23 responses)- A91% (21)
- B4% (1)
- C4% (1)
Why each option
The project charter is developed during the initiating process group, which typically occurs at the beginning of a project or phase, often referred to as pre-project setup.
The project charter is created in the Initiating Process Group, which is the first of the project management process groups, to formally authorize the project or a project phase and appoint the project manager. 'Pre-project setup' accurately describes this initial authorization stage.
Project execution involves performing the work defined in the project management plan, which happens after the project charter has been developed and approved.
Project planning involves defining objectives, refining scope, and developing the project management plan, all of which occur after the project has been formally authorized by the charter.
Project control involves monitoring, measuring, and correcting project performance throughout the execution phase, long after the charter is created.
Concept tested: Project charter and initiating process group