nerdexam
CompTIA

PK0-003 · Question #190

In which of the following situations would a project manager conduct a post mortem?

The correct answer is A. The project sponsor stopped the project.. A project manager conducts a post-mortem, or lessons learned session, at the conclusion of a project, whether it finishes successfully or is terminated.

Project life cycle phases

Question

In which of the following situations would a project manager conduct a post mortem?

Options

  • AThe project sponsor stopped the project.
  • BA key stakeholder is upset with the quality of a deliverable.
  • CA new project manager has been assigned to the project.
  • DTo determine why the change control board rejected a change request.

How the community answered

(46 responses)
  • A
    96% (44)
  • B
    2% (1)
  • C
    2% (1)

Why each option

A project manager conducts a post-mortem, or lessons learned session, at the conclusion of a project, whether it finishes successfully or is terminated.

AThe project sponsor stopped the project.Correct

A project termination, such as when a project sponsor stops the project, represents a definitive end point where a post-mortem is crucial. This process documents lessons learned from the entire project lifecycle, including reasons for termination, to benefit future projects regardless of the outcome.

BA key stakeholder is upset with the quality of a deliverable.

A stakeholder being upset with quality is an issue addressed during project execution and quality control, not an event that triggers a project-level post-mortem.

CA new project manager has been assigned to the project.

A new project manager being assigned is an internal staffing change requiring a handover, not a project completion or termination that necessitates a post-mortem.

DTo determine why the change control board rejected a change request.

Investigating a rejected change request is part of ongoing change control and problem-solving during project execution, not an end-of-project post-mortem activity.

Concept tested: Project management project closure and lessons learned

Topics

#Project closure#Lessons learned#Post-mortem review

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice