PK0-003 · Question #158
If the SPI and CPI are both above 1, then the project is:
The correct answer is D. Ahead of schedule and under budget.. If both the Schedule Performance Index (SPI) and Cost Performance Index (CPI) are greater than 1, the project is performing better than planned regarding both schedule and budget.
Question
If the SPI and CPI are both above 1, then the project is:
Options
- ABehind schedule and under budget.
- BBehind schedule and over budget.
- CAhead of schedule and over budget.
- DAhead of schedule and under budget.
How the community answered
(43 responses)- B5% (2)
- C7% (3)
- D88% (38)
Why each option
If both the Schedule Performance Index (SPI) and Cost Performance Index (CPI) are greater than 1, the project is performing better than planned regarding both schedule and budget.
An SPI above 1 indicates ahead of schedule, not behind.
An SPI above 1 indicates ahead of schedule, not behind, and a CPI above 1 indicates under budget, not over.
A CPI above 1 indicates under budget, not over.
An SPI greater than 1 indicates that more work has been completed than planned, meaning the project is ahead of schedule. A CPI greater than 1 indicates that the actual cost for the work performed is less than the planned cost, meaning the project is under budget.
Concept tested: Earned Value Management (EVM) metrics