Which of the following BEST describes a project risk?

The correct answer is A. Something that may positively or negatively impact the project. A project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives.

Project management concepts

Question

Which of the following BEST describes a project risk?

Options

  • ASomething that may positively or negatively impact the project
  • BSomething that has already affected the project
  • CSomething that is outside of the control of the project manager
  • DSomething that will negatively impact the project

How the community answered

(53 responses)
  • A
    92% (49)
  • B
    2% (1)
  • C
    2% (1)
  • D
    4% (2)

Why each option

A project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives.

ASomething that may positively or negatively impact the projectCorrect

A project risk is defined as an uncertain event or condition that, if it occurs, has a potential effect on project objectives, which can be either positive (an opportunity) or negative (a threat).

BSomething that has already affected the project

Something that has already affected the project is an issue, not a risk, as its uncertainty has passed.

CSomething that is outside of the control of the project manager

While many risks are outside direct control, the definition of a risk primarily focuses on its uncertain nature and potential impact, not just the level of control.

DSomething that will negatively impact the project

This only covers negative risks (threats) and omits positive risks (opportunities), making it an incomplete description.

Concept tested: Project risk definition and types