nerdexam
CompTIA

PK0-003 · Question #159

Which of the following is the BEST description of a baseline?

The correct answer is C. A snapshot of the project at a particular point in time. A project baseline represents a frozen point-in-time snapshot of the approved plan against which project performance is measured and controlled.

Project management concepts

Question

Which of the following is the BEST description of a baseline?

Options

  • AA view of the project's status
  • BAn assessment of risks for the project
  • CA snapshot of the project at a particular point in time
  • DA calculation of the project's CPI and SPI

How the community answered

(30 responses)
  • B
    3% (1)
  • C
    93% (28)
  • D
    3% (1)

Why each option

A project baseline represents a frozen point-in-time snapshot of the approved plan against which project performance is measured and controlled.

AA view of the project's status

A view of the project's status is a current report, not the unchanging reference point that a baseline represents.

BAn assessment of risks for the project

An assessment of risks is part of risk management, which is an input to or a component tracked against a baseline, but not the baseline itself.

CA snapshot of the project at a particular point in timeCorrect

A baseline is a formally approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison. It effectively serves as a snapshot of the project's plan at a specific moment.

DA calculation of the project's CPI and SPI

CPI and SPI are performance indicators calculated from the baseline, not the definition of the baseline itself.

Concept tested: Project baseline definition

Topics

#project baseline#scope baseline#schedule baseline#cost baseline

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice